THE WHY AND WHEREFORE
With very limited hydrocarbon resources, Quebec and Ontario must import
almost all the natural gas they consume. In this regard, Quebec and Eastern
Ontario are doubly dependent, since their gas comes exclusively from
sedimentary basin deposits in Western Canada and is imported using a single
means of transport-the TransCanada pipeline network.
This double dependence makes both regions highly vulnerable,
particularly because gas prices are subject to the pressures of supply and
demand, and both provinces are at the eastern tip of the TransCanada
pipeline.
Today, natural gas meets about 12% of Quebec's energy needs and 34% of
Ontario's.
Steady growth in the use of this form of energy has occurred not only in
Quebec and Ontario, but throughout North America. Natural gas is becoming
increasingly popular thanks in part to characteristics that make it
especially attractive, particularly lower greenhouse gas (GHG) emissions
than other fossil fuels.
However, natural gas production is rapidly leveling off in North
America, which holds about 4% of the world's reserves and consumes some 30%
of worldwide supply.
While natural gas prices are rising in North America as conventional
deposits are depleted, demand for this form of energy is steadily
growing.
This trend was particularly pronounced in 2005, when climate-related
natural disasters caused natural gas prices to surge to levels three to
four times higher than in the late 1990s.
The goal of the Rabaska LNG terminal project is to give Quebec and
Eastern Ontario an alternative gas supply source. In addition to ensuring a
more secure supply, increased resource availability will create a more
competitive environment that will benefit all consumers, particularly the
some 50,000 commercial, industrial, and institutional customers in Quebec
who now use natural gas.
Studies ordered by Rabaska—notably from Energy and Environmental Analysis Inc. (EEA)—show that the project could lead to an approximate 5% drop in natural gas prices. The EEA study can be consulted in Volume 2, Appendix G of the Rabaska impact study at http://www.rabaska.net/pdf_toc1.html.
LNG transport technology, used for over 40 years in many regions of
Europe, Asia, and the United States, was developed to bring consumer
countries closer to the large reserves of many producer countries. It
offers an attractive alternative as North American resources are
depleted.
When natural gas is liquefied after been cooled to -160°C, it
takes up only 1/600th of its volume in a gaseous state. Liquefied natural
gas can be transported by ship economically and safely.
Increased natural gas use also helps meet the greenhouse gas (GHG)
emission reduction objectives set out in the Kyoto Protocol by replacing the
consumption of fuel oil and coal, which emit millions of tons of GHG and
pollutants into the atmosphere each year.
THE PARTNERS
The project promoter is Rabaska, a limited partnership made up of Gaz
Métro, Enbridge, and Gaz de France. These firms have pooled their resources
and experience to build and operate the LNG terminal.
The impressive combined resources and expertise of these three partners
provide assurance that the highest quality standards will be met in the
design, development, and operation of the future Rabaska LNG terminal, as
well as the gas pipeline that will link it to the interprovincial transport
and distribution network.
|
With over $2 billion in assets and more than
1,500 employees in Quebec, Gaz Métro is a major Quebec energy company and
one of the biggest natural gas distributors in Canada. Gaz Métro delivers
97% of the natural gas consumed annually in Quebec. Founded almost 50 years
ago, the company serves some 157,000 Quebec customers with an underground
pipeline network extending close to 10,000 kilometers. A Canadian gas
industry leader, Gaz Métro has operated one of only three LNG liquefaction, storage, and
regasification sites in the country for almost 35 years. Its liquefied
natural gas (LNG) facility is located in east-end Montreal. |
|
With over 4,000 employees, Enbridge is one of
the largest energy transport firms in North America and operates the
longest liquid hydrocarbon transport network in the world. Its pipelines
extend more than 40,000 kilometers. It has had a hand in developing many
oil terminals throughout North America and worldwide. It operates 11 crude
oil and liquid hydrocarbon terminals, as well as three oil tank farms. It
also owns Enbridge Gas Distribution, Canada's largest natural gas
distributor serving approximately 1.7 million customers, primarily in
Ontario. |
|
With a stock exchange valorization of 35 billion euros, over
50,000 employees, and some 13.8 million customers, Gaz de France is an
integrated group that plays a key role throughout the natural gas supply
chain in France. Gaz de France is currently one of the world's leading LNG
purchasers and has been actively developing and applying LNG technology for
more than 40 years. Currently operating two LNG terminals in France and
with a third under construction, the group boasts recognized expertise in
LNG terminal and tanker design, construction, and operation. |
THE TERMINAL
The purpose of an LNG terminal is to accommodate LNG tankers, unload their
cargo, and temporarily store it in tanks before vaporizing it, i.e.,
returning it to its original gaseous state. The gas is then pumped
continuously into the interprovincial transport network, and from there to
the Quebec and Ontario distribution networks.
LNG terminal designers make technical design choices that influence
various aspects of the project. Below are some of the solutions chosen for
the Rabaska terminal, together with their main advantages:
• Tanker accommodation
To safely accommodate tankers, the water must be at least 15 meters
deep. Rabaska designers opted for a finger pier and jetty extending out
over the river instead of dredging the riverbed and building a shorter
jetty. In order to minimize disruption to aquatic wildlife and impact on
the environment, they also opted for a pile jetty rather than a rock
jetty.
• Tanker unloading
While new technologies are currently under development, the only proven
technology currently available is the "jointed" offloading arm. This
technology was therefore chosen for tanker unloading operations.
• Offloading lines
The two cryogenic steel pipes that will link the finger pier to the LNG
tanks will be placed inside a buried, climate-controlled concrete caisson
to prevent corrosion. By choosing this option over aerial offloading lines,
the designers have not only improved facility safety but also significantly
reduced the visual impact of this essential facility component.
• LNG storage tanks
After being unloaded from the tankers, the LNG is temporarily stored in
tanks to await vaporization and then release into the pipeline network for
delivery to consumers. The tanks built in Lévis will consist of two
containers, one inside the other. The internal tank will be made of
cryogenic steel, and the outer wall of prestressed concrete approximately 1
meter thick. These tanks are called "failsafe" because they are designed to
prevent any uncontrolled emission of liquid or gas into the atmosphere,
even in the event of a leak in the internal tank. This technology is
assuredly the best and safest to date. In addition, the tanks will be
placed at the center of retention basins 10 meters deep capable of holding
the entire amount of LNG.
• LNG energy value adaptation
Most of the LNG delivered to Lévis will have an energy value that will
need to be adjusted before it is released into the transport network and
distributed to consumers. Rabaska engineers have chosen a solution that
consists of injecting a small amount of nitrogen into the natural gas to
adjust its calorific capacity through dilution.
• LNG vaporization or regasification
Before it is released into the pipeline network, the LNG must be
reheated and returned to a gaseous state. Of the various technologies
available for this process, Rabaska engineers have chosen "submerged
combustion regasifiers." This technology consists of circulating LNG
through coiled pipes submerged in water heated by natural gas burners. It
uses little water and is both efficient and able to adapt to variations in
flow. It is certainly the best-suited technology to the climatic and
environmental conditions on site.
- Guardhouse
Access to the site is permanently controlled by
dedicated personnel in the guardhouse and, when a vessel is docked, in the
jetty security hut (located at the entrance to the jetty area, north of
Route 132). The entire Rabaska facility will be protected by a
security perimeter that is monitored 24 hours a day by an electronic
surveillance system and periodic rounds by security personnel.
- Administration
The administrative building will house various
operations and administrative functions, as well as Rabaska management.
- Workshop and warehouse
The bulk of maintenance operations will be conducted
onsite by terminal personnel, who will have the workshops, rooms, and
equipment required to perform this work.
- Fire station
Terminal employees will be trained in firefighting
and have all the equipment they need, including individual protective
suits, mobile equipment (trucks, mobile extinguishers), and fixed equipment
(see 7 and 8) to respond as quickly as possible in the event of an
accident.
- Control room
Round-the-clock human and computer surveillance of
the entire LNG terminal will be conducted from the control room. Backup
diesel generators will supply power to essential personnel and facility
safety equipment in the event of an outage, even if it is prolonged.
- Laboratory
The laboratory will be used to store gas samples
(outside), conduct occasional analyses, and check the calibration of
automatic analyzers installed closest to the facility.
- Fire water storage tank and fire pumps
A 7,000 m3 fire water storage tank in
which electric and diesel fire pumps are submerged will supply a
facility-wide network and provide the water required by all fixed
firefighting equipment (distribution lines, foam generators, fire hydrants
and nozzles, etc.).
- Utility building
The utility building will include a variety of
equipment required for terminal operation: compressed air production, etc.
- Main substation
The terminal will be supplied by two 230 kV
Hydro-Québec powerlines. The main substation will include transformers,
switches, and electrical panels to reduce voltage and distribute power to
the entire terminal.
- Nitrogen production unit
Nitrogen will be used primarily to adjust the energy
value of the natural gas released into the transport network. It will be
manufactured onsite from three cryogenic air fractionation units that
produce 99.99% pure nitrogen gas. This conventional process based on the
compression, cooling, and depressurization of the elements in air
(nitrogen, oxygen, and argon) uses no other coolant.
- Gasline loading station
When the gas leaves the metering station, it will be
released into the transport network via the gasline loading station. An
emergency shutdown valve will isolate the terminal from the pipeline in the
event of an accident at either end. A pigging station will be used for
pipeline maintenance operations.
- Vaporizers
Submerged combustion vaporizers will progressively
heat the LNG to return it to a gaseous state. This technology consists of
circulating the LNG through coiled pipes entirely submerged in warm water.
Natural gas burners maintain the water temperature between 20°C and 50°C,
and the combustion smoke bubbles through the water bath, ensuring maximum
energy efficiency (nearly 100%).
- Dispatch pumps
Each tank will be equipped with a number of
low-pressure drawdown pumps submerged in the LNG. These will force the LNG
toward the high-pressure dispatch pumps, which will raise its pressure to
that of the pipeline network.
- Boiloff gas compressors
Despite the high quality of insulation materials, a
minimal amount of heat reaches the equipment that contains the LNG, causing
slight evaporation of the LNG. The evaporated gas is recovered and later
reincorporated into the LNG using boiloff gas compressors and a
recondenser. Thanks to this recovery process, the terminal produces no
natural gas emissions during normal operations.
- Failsafe double-walled LNG tanks
Measuring 90 meters in diameter and 46 meters high,
the two tanks can each hold 160,000 m³ of LNG at -160°C and virtually
atmospheric pressure. The outer tank wall will be made of 90 cm thick
prestressed concrete, and the inner tank containing LNG will be made of
cryogenic steel ranging in thickness from 1 cm at the top to 3 cm at the
base. It will be surrounded by approximately 1 meter of thermal
insulation. All pipelines transporting LNG will pass through the
top of the tanks to ensure complete tank wall integrity.
- Tertiary retention basin
The two LNG tanks will be built right on the rock in
a 10 meter deep basin. The basins will measure approximately 150 meters
wide by 150 meters long. These basins will help significantly reduce the
project's visual impact.
- Flarestack
The flarestack is a safety device that will safely
evacuate the gas in the event of stoppage of the evaporation recovery
equipment. Aside from its pilot, the stack will not be activated during
normal terminal operation.
- Debris basin
During operation, as during the construction phase,
drainage ditches will help collect runoff in contaminant-free areas. This
water will be routed to a debris basin before it is released into
Saint-Claude Creek. As needed, the basin will be equipped with filtration
devices, and quality controls will be performed.
- Measuring station
On leaving the vaporizers, the natural gas will be
routed to a commercial measuring station in order to determine the volume
and composition of the gas released into the transport network.
- Service corridor
A service corridor approximately 1.3 km long will
accommodate the various pipes and connections needed to link the shore and
land facilities. It will include two LNG discharge lines, one natural gas
pipe, compressed air and water pipes, electric cables, and a service
corridor for the use of terminal personnel.
The LNG and gas pipes will be made of cryogenic
stainless steel. They will be insulated, designed to withstand very low
temperatures, and protected inside a concrete caisson buried beneath the
ground between the river and the land facility. Pipe segments will be
welded to prevent LNG leaks.
- Shore facility
The shore facility will be built on a rock platform.
It will primarily be made up of the LNG pressurization pumps that force the
LNG toward the tanks when tankers are unloaded.
- Jetty
The jetty will accommodate LNG tankers. It will
include the finger pier, nine docking/berthing structures, and an
approximately 500 meters trestle bridge connecting the finger pier to the shore
facility.
The finger pier will be located in water 15 meters deep
(at low tide) to accommodate tankers without having to dredge the St.
Lawrence River bed. The finger pier and docking/berthing structures will be
designed to withstand the pressures caused by tankers, seismic activity,
and ice.
The jetty will be equipped with four offloading arms
for transferring the LNG from the tankers to the storage tanks on land.
- Concealment berms
Concealment berms will be set up around the terminal
to reduce its visual impact, notably from Route 132 and Île d'Orléans.
These berms will be planted with vegetation to blend in with the existing
landscape. To the south, the existing wooded area will be extended to
reduce the visual impact from homes located south of Highway 20 and from
the highway itself.
- New Saint-Claude Creek bed
Before work begins, Saint-Claude Creek-which
currently runs through the site-will be rerouted south of the worksite. Its
new banks will be revegetated to provide a new habitat for local
wildlife.
- Tunnel under Route 132
When work starts, a tunnel will be built under Route
132 to enable workers and trucks to travel to and from the worksite without
interfering with local traffic.
- Terminal access road
The main access road for personnel and visitors will
be from Route Lallemand to the western entrance of the site.
THE PIPELINE
The Rabaska LNG terminal will be connected to the Canadian gas transport
network through an underground pipe linking the Lévis facility to the TQM
Pipeline distribution station next to Jean-Lesage Highway in
Saint-Nicolas.
This natural gas can meet the needs of all Quebec and Eastern Ontario customers.
The 610 mm (24") diameter pipe will extend approximately 42 kilometers.
It will be installed in a permanent right-of-way 23 meters wide at a
general depth of 1.2 meters in farmland and 0.9 meters in woodland. The
maximum operating pressure will be 9,930 kPa.
Some sections of the pipeline will be parallel or adjacent to the proposed St. Lawrence Pipeline, which will allow the Jean Gaulin refinery in Lévis to be linked to Ultramar's Montreal facilities. For these sections, the width of the permanent right-of-way will be reduced from 23 meters to 18 meters.
The pipe will require installation of a delivery gate adjacent to that
of TQM Pipeline, as well as a pigging station and an automatic block valve
at each end. A third block valve will be placed approximately midway. The
proposed pipeline, construction of which will take 12 months,
represents an investment of over $65 million.
(Click map to zoom in)
MAIN TECHNICAL SPECIFICATIONS
- Gas pipeline diameter: 610 mm
- Operating pressure: 9,930 kPa
- Approximate length: 42 km
- Minimum ground cover:
-
Woodland: 0.9 meters
-
Farmland: 1.2 meters
-
Regulated watercourse: 1.5 meters
- Cathodic protection
- Automatic block valves
- Permanent easement width: 23 meters (18 meters for the section parallel to the St-Lawrence Pipeline)
- Width of temporary worksites required during construction: 10 meters, adjacent to
permanent easement
-
Temporary worksites of varying dimensions for the clearing of obstacles
- Delivery gate to be built near the TQM Pipeline gas
facility
- Construction and design in accordance with the norms and
standards in effect
MAIN MAINTENANCE AND SURVEILLANCE OPERATIONS
- Air and land patrols
- Maintenance of the permanent easement to sustain herbaceous
plant growth
- Network surveillance 365 days a year, 24 hours a day from the
control station
- Pipe interior inspection program
The gas pipeline will be added to the marine and land facilities to transport
natural gas from the LNG terminal to Saint-Nicolas for distribution by TQM
Pipeline.
A new supply source will lead to changes to the TQM Pipeline and probably also to the TransCanada facilities
needed to distribute and then transport the required volumes from
Saint-Nicolas to the West. Essentially, the pipeline between Saint-Nicolas
and Saint-Augustin-de-Desmaures will have to be doubled over a total length
of approximately 13.5 kilometers, including 3.6 kilometers in the existing under-river
tunnel. Two compression stations will also have to be added between
Saint-Nicolas and Montreal. Work will be completed by TransCanada and TQM
Pipeline after obtaining the required authorizations.
The electricity required for Rabaska operations will be supplied by two
new 230 kV powerlines that will link the terminal to existing lines south
of Chemin Saint-Roch, approximately 1.5 kilometers from the terminal. Three or four
towers per line with a combined right-of-way of about 60 meters will have
to be built to link the terminal to the existing lines. Hydro-Québec will
oversee construction of these powerlines after obtaining the required
authorizations.
|